Articles / Technology and smart buildings
The ICT Checklist for an Office Fitout
An ICT checklist for an office fitout covers carrier lead times, the comms room, data cabling, wireless design, security systems, AV, furniture coordination, testing, cutover and handover. Start the ICT workstream at concept design, because carrier connections and equipment often take longer than the construction itself. Work through the list below with your project manager, ICT lead and builder.
Why does ICT need its own checklist?
ICT is often the last thing considered and the first thing blamed when a new office opens poorly. If the network is slow or the meeting rooms fail on the first Monday, the whole fitout disappoints, whatever the finishes look like.
The reason is simple. ICT touches almost every other trade. Cabling runs through ceilings and walls. Equipment needs power and cooling. Furniture contains outlets. Security systems share infrastructure. Carrier connections enter through the base building, which involves the landlord.
In my experience, the projects that go smoothly treat ICT as a design discipline from the start, with its own scope, budget line and programme of tasks. The checklist below follows a typical sequence for a Sydney office. Details vary by building and organisation. Adapt it to your circumstances.
The ICT checklist for an office fitout, step by step
- Define the requirements. Document how many people, devices and meeting rooms the office will support, along with application needs, security obligations and growth expectations. Everything else flows from this brief.
- Review the base building. Ask the landlord about available risers, conduits, entry points and carrier access. Some buildings offer multiple carriers, while others restrict choice. Confirm any approvals needed for works in common areas.
- Order carrier services early. Internet and network circuits can take many weeks or months, particularly when new fibre or building access is needed. Place orders as soon as the lease and location are certain, and confirm the delivery date in writing. Consider a second diverse circuit for resilience.
- Plan the comms room. Decide its size and position at concept design. Allow for racks, power, cooling, fire protection, access control and room to expand. Avoid locations near water pipes or risk of flooding. Consult your ICT team and engineer about the cooling load.
- Design data cabling. Choose a cabling standard and quantity of outlets per workstation, meeting room and common area, with spare capacity. Define the paths from comms room to outlets, labelling conventions and test requirements.
- Design the wireless network. Base the design on a predictive survey, then validate after installation. Consider density in meeting rooms and break areas, building materials, interference and guest access. Wireless design and cabling should be developed together, because access points need data cables and power.
- Coordinate security systems. Access control, CCTV and intruder alarms rely on cabling and network connections. Agree who supplies, who installs and who maintains each element, and check compatibility with base building systems.
- Integrate AV. Meeting rooms, boardrooms and collaboration spaces need data, power, ceiling and wall provisions. Bring the AV designer into the team early, as discussed in my article on workplace AV design.
- Coordinate with furniture. Desks, joinery and meeting tables often contain power and data outlets. Confirm outlet types, cable paths and the sequence of installation with the furniture supplier and the builder.
- Plan printing, phones and specialist equipment. Confirm the quantities and locations of printers, handsets and other specialist devices.
- Order equipment. Network switches, wireless access points and firewalls all carry lead times. Place orders in line with the construction schedule.
- Inspect during construction. Visit the site at key stages, such as cabling rough in before ceilings close. Fixing a problem above an open ceiling costs far less than after the ceiling is complete.
- Test and certify. Cabling should be tested and certified, with results provided in a report. Wireless coverage should be measured. Network performance, failover and security configurations should be checked against the design.
- Plan the cutover. Decide how and when users and systems move to the new office. Prepare a detailed plan with tasks, owners, timing, rollback options and communications.
- Support the first days. Arrange extra support on site for the first week, with a clear route for staff to report issues.
- Complete handover. Collect as built drawings, cable schedules, test results, configuration records, warranties, licences and manuals.
What should the comms room include?
The comms room is the heart of the office network, and mistakes there are expensive to correct. Think about the following: * Size and position. Choose a location that is central enough for cable length limits, secure and easy to reach. * Power. Provide dedicated circuits, and consider backup power for critical equipment. * Cooling. Equipment generates heat. Confirm whether the base building air conditioning can serve the room, or whether a dedicated unit is needed. * Security. Restrict access and record who enters. * Cable management. Neat racks, labelled cables and adequate space make faults quicker to find. * Growth. Leave room for additional racks and equipment as the organisation changes.
Many organisations now use cloud services heavily, which reduces on site equipment, yet a comms room remains necessary for network and security gear. Your ICT team should determine a sensible size.
How do cabling and wireless design fit together?
People often ask whether wireless makes cabling redundant. In my view, the answer is that wireless increases the importance of cabling. Every access point needs a data cable and power, and wireless performance depends on its placement.
A sound approach is to design for how people work. In a hybrid office, where many people use laptops and move between desks, meeting rooms and collaboration areas, wireless carries much of the load. Fixed cabling still serves docking stations, printers, AV equipment, security devices and specialist uses.
Ask your designer to explain the assumptions behind the number of outlets and access points, and to include a validation survey after construction.
How do you plan testing, cutover and handover?
Testing proves the work, cutover moves people across, and handover prepares the organisation to run the new environment.
For cutover, choose a date that allows a buffer after practical completion. Pre configure equipment off site where possible. Prepare staff communications, including how to connect, where to get help and what changes. Keep a rollback plan for critical services.
For handover, ask for complete documentation and training for the support team. Agree defect rectification and warranty arrangements in writing. A short review after one month captures lessons and fixes lingering issues.
Frequently asked questions
How early should I order carrier services for a new office?
Order as soon as the lease and location are confirmed. Carrier lead times vary with building access, fibre availability and approvals, and can run for many weeks or months. Ask the carrier for a written delivery date and confirm it with the landlord. Consider a second diverse circuit for resilience.
How big should a comms room be?
Size depends on the number of users, racks, cooling needs and expected growth. Your ICT team or consultant should calculate it from the design brief and leave space for expansion. Include power, cooling, security and clear access in the design. Confirm requirements early, because the room affects layout and services.
Should I rely on wireless instead of data cabling?
Wireless carries most day to day connections in a modern office, yet cabling remains essential. Access points need data cables, and fixed connections serve docking stations, printers, AV and security equipment. Design both together, based on predictive surveys, and validate the wireless performance after installation.
What documents should I receive at handover?
Ask for as built drawings, cable schedules, test and certification reports, network configurations, equipment lists, warranties, licences and manuals. Also request training for your support team and a defects process. Complete documentation makes future changes and fault finding far easier, particularly when staff or suppliers change.
Who should lead the ICT workstream?
Appoint a named ICT lead, either internal or a specialist consultant, who works with the project manager, designers and builder. This person owns the requirements, coordinates suppliers, signs off testing and manages cutover. Clear ownership prevents tasks falling between teams.
Final thoughts
Work through this ICT checklist for an office fitout early, assign an owner to every line and revisit it at each design milestone. Offices that open with reliable technology have usually planned for it from the first week of the project.
If you would like more practical Sydney property insight, subscribe to my newsletter, The Fine Print, on LinkedIn and follow along.
The Fine Print
Plain talk on Sydney property, delivered through LinkedIn. Subscribe to The Fine Print by Denise Masters and follow along for new articles.
Subscribe on LinkedIn